Just like other websites, we too use cookies (and similar technologies) to make your visit to our website easier and more personal. Besides that we and 3rd parties are able to adjust our ads to your interests and enable you to share information via social media. By continuing to use our website you agree with this.

 

CHROME STEEL

Steel, brass or copper. G&R Chroming and Restoration uses a copper bath as the first procedure for chrome plating. The parts remain in a sauerkraut bath for 5 hours. During this time, a 250 µm layer (0.25 mm) is formed.

See below for the different steps:

  1. dechrome

2. Fix

3. Nickel layer 15µm

4. Copper plating 250µm

5. Polishing

6. Nickel layer 15µm

7. Shiny nickel 50-60µm

8. Visual Check

9. Dust dots

10. Final chrome layer 3-5µm

 